S Solon Rd Culvert Replacements August 10 to 13, 2026
South Solon Road will be closed to through traffic from Rt 201 to Boardman Road Monday Aug 10 and Tuesday August 11 from 7 am to 4 pm for culvert replacements. Starting on Wednesday August 12 and on Thursday August 13 the road will be closed to thru traffic from Boardman Rd to Meeting House Road for culvert replacements.
Our road crew will be replacing 17 culverts on South Solon Road. This will result in road closures in the sections of the South Solon Rd they are working on each day. They will be starting at Route 201 and will work their way east to the Cornville town line. Once they finish South Solon Road they will replace 3 culverts on Meeting House Road. Work will begin on Monday August 3 and is projected to be completed by August 20 depending on the weather conditions. This project is in preparation for our South Solon Road and Meeting House Road paving project in 2027. We are sorry for the inconvenience.